One Person Lifting Efficiency
Pronomic
The Operational Math: How One-Person Lifting Transforms Labour Capacity
Converting two-person tasks to one-person work isn't just about reducing headcount. It's about reallocating scarce skilled labour toward higher-value work while compressing installation windows and reducing scheduling pressure.
The Starting Point: Two-Person Handling
Data center installations, swaps, and battery moves have traditionally required two technicians sometimes even more. The reasons are sound: stability, alignment precision, and safety redundancy. But the consequence is significant: every task consumes twice the labour.
At scale, this becomes a bottleneck. A facility performing 2,000 server moves per year, at 30 minutes per move with two technicians, consumes 1,000 labour-hours annually—labour that could otherwise go toward higher-value work like troubleshooting, optimization, or customer support.
One-Person Capable Equipment Changes the Equation
When lifting equipment provides the stability and alignment traditionally provided by a second person, the math shifts dramatically:
Labour Impact:
-
Traditional: 2 techs × 30 min = 1 labour-hour per move
-
With engineered lifter: 1 tech × 30 min = 0.5 labour-hours per move
-
Savings per move: 0.5 labour-hours
-
Annual impact (2,000 moves): 1,000 labour-hours freed
What You Do With Those Hours
That's not just a cost reduction—it's a capacity multiplier:
-
Higher-Value Work - Reallocate technicians to optimization, monitoring, customer escalations, and complex troubleshooting.
-
Schedule Compression - Complete migrations in tighter windows without overtime. Reduce backlog risk and improve customer SLAs.
-
Staffing Flexibility - With fewer bodies required per task, you adapt to turnover and vacation coverage without crisis management.
-
Talent Retention - Easier work feels better. Less strain, less fatigue, lower MSD risk = better engagement.
Supporting the Talent Shortage
Getting more productive output from your current team—without adding headcount—directly addresses this constraint.
One-person-capable equipment is therefore both a productivity play and a talent retention strategy.
Supporting Data
-
Annual moves per facility: 1,000–5,000 (varies by size and refresh cycle)
-
Labour savings per move: 0.5 labour-hours
-
Facility-level annual savings: 500–2,500 labour-hours
-
At EUR100/hour fully loaded cost: EUR 50,000–EUR 250,000 per facility annually